The Michigan Department of Transportation (MDOT) will soon begin repaving M-19 (Gratiot Avenue) between New Haven and 31 Mile roads, covering almost 6 miles in the village of New Haven, the city of Richmond and Lenox Township. Click on the link below to view the MDOT Press Release.
Beginning in late April through mid-August, crews will be performing a variety of work in different locations and schedules. Work in this project includes removing and replacing asphalt, performing joint repairs, drainage improvements, curb ramp upgrades and permanent pavement markings.
Late April to mid-August:
- 9 a.m. - 6 p.m. Monday-Friday: one lane open under flag control.
- 7 a.m. - 6 p.m. Saturday-Sunday: one lane open under flag control.
This flag control on M-19 (Gratiot Avenue) will be performed in half-mile sections starting near New Haven Road toward 31 Mile Road. The work schedule will normally occur Monday-Friday unless weather or delays require weekend work.
Late April to mid-May:
- Joint repairs on M-19 (Gratiot Avenue) between New Haven Road and 31 Mile Road under flag control.
Mid-May to mid-June:
- M-19 (Gratiot Avenue)/31 Mile Road intersection work for drainage and driveway improvements.
Mid-June to late July:
- Milling and resurfacing on M-19 (Gratiot Avenue) from New Haven to 31 Mile roads.